Year

CAT 2018

Section

Quantitative

Topic

Time and Work

Difficulty

Hard

Question

Slot-2

Ramesh and Ganesh can together complete a work in 16 days. After seven days of working together, Ramesh got sick and his efficiency fell by 30%. As a result, they completed the work in 17 days instead of 16 days. If Ganesh had worked alone after Ramesh got sick, in how many days would he have completed the remaining work?

12

14.5

13.5

11