CAT 2018 Time and Work — Previous Year Question
Year
CAT 2018
Section
Quantitative
Topic
Time and Work
Difficulty
Hard
Question
Slot-2
Ramesh and Ganesh can together complete a work in 16 days. After seven days of working together, Ramesh got sick and his efficiency fell by 30%. As a result, they completed the work in 17 days instead of 16 days. If Ganesh had worked alone after Ramesh got sick, in how many days would he have completed the remaining work?
12
14.5
13.5
11