CAT 2021 Time and Work — Previous Year Question
Year
CAT 2021
Section
Quantitative
Topic
Time and Work
Difficulty
Medium
Question
Slot-2
Given: Anuj takes 1 day to complete a job. Bharat takes twice the time as Anuj to complete the same job. Chetan takes twice the time as Bharat to complete that job. Dhiraj takes twice the time as Chetan to complete that job.
(A) Chetan and Dhiraj will take 8/3 days to complete the work (B) The second fastest pair to complete the work is Anuj and Dhiraj (C) The second slowest pair to complete the work is Bharat and Dhiraj (D) Bharat and Dhiraj will take 4/3 days to complete the work
Choose the correct answer from the options given below:
(A), (B) and (C) only
(A) and (D) only
(A) and (C) only
(A) only
Stand Out in Your CAT Interview Round!
Build confidence with mock interviews tailored to IIM and top B-school patterns. Get instant feedback from mentors.
Explore Interview Platform