CAT 2024

Section

Quantitative

Topic

Time and Work

Difficulty

Hard

Question

Slot-2

Amal and Vimal together can complete a task in 150 days, while Vimal and Sunil together can complete the same task in 100 days. Amal starts working on the task and works for 75 days, then Vimal takes over and works for 135 days. Finally, Sunil takes over and completes the remaining task in 45 days. If Amal had started the task alone and worked on all days, Vimal had worked on every second day, and Sunil had worked on every third day, then the number of days required to complete the task would have been

Ace Your MBA Admission Interviews!

Comprehensive interview preparation covering behavioral questions, case studies, and situational scenarios for MBA admissions.

Explore Interview Platform

Loading...

logo
optima learn

Optima Learn — Powered by Optimum Eduteck Pvt. Ltd. Built by learners from FMS Delhi, DTU, and Microsoft. contact@optimalearn.com

Connect with us

LinkedInInstagram

© 2026 Optima. All rights reserved.