CAT 2020 Time and Work — Previous Year Question
Year
CAT 2020
Section
Quantitative
Topic
Time and Work
Difficulty
Medium
Question
Slot-3
A contractor agreed to construct a 6 km road in 200 days. He employed 140 persons for the work. After 60 days, he realized that only 1.5 km road has been completed. How many additional people would he need to employ in order to finish the work exactly on time?